Argentina launches AlmaSADI tender for 700 MW of battery energy storage systems (BESS)
Type: Development · Technology: Storage · Country: Argentina · Capacity: 700 MW · Value: $700M · Announced: 2026-03-16
Argentina's Compañía Administradora del Mercado Mayorista Eléctrico SA (CAMMESA) and the national Secretariat of Energy launched the AlmaSADI tender, seeking 700 MW of stand-alone Battery Energy Storage Systems (BESS) across multiple nodes in the country's 132 kV and 220 kV electrical networks. The initiative, estimated at USD 700 million, aims to enhance grid stability and operational flexibility by distributing storage capacity across strategic locations in provinces like Córdoba, San Luis, and Buenos Aires. Projects awarded under the tender will secure 15-year contracts with CAMMESA as the offtaker, with remuneration primarily based on power availability and frequency regulation services. Technical and administrative offers are due by May 8, 2026, with economic offers opening on June 5, 2026, and final awards scheduled for June 19, 2026. Contract signing is set for June 25, 2026, with commercial operation of the awarded projects targeted by December 31, 2029.
Analysis
Argentina's Compañía Administradora del Mercado Mayorista Eléctrico SA (CAMMESA) and the national Secretariat of Energy launched the AlmaSADI tender on March 16, 2026, seeking 700 MW of stand-alone battery energy storage systems (BESS) across multiple nodes in the country's 132 kV and 220 kV electrical networks. The tender covers projects in provinces including Córdoba, San Luis, and Buenos Aires, with technical and administrative offers due by May 8, 2026, and economic offers to be opened on June 5, 2026. Final awards are scheduled for June 19, 2026, with contract signing set for June 25, 2026, and commercial operation required by December 31, 2029. Projects will receive 15-year contracts with CAMMESA as offtaker, remunerated based on power availability and frequency regulation services.
Key points
- 700 MW of battery energy storage capacity sought
- Projects located across 132 kV and 220 kV networks in Córdoba, San Luis, and Buenos Aires provinces
- Technical and administrative offers due May 8, 2026; economic offers opened June 5, 2026
- 15-year contracts with CAMMESA as offtaker, remuneration based on availability and frequency regulation
- Commercial operation required by December 31, 2029