Baltic Power completes transition piece installation for 1.2GW Polish offshore wind farm
Baltic Power has successfully installed all 76 transition pieces at its 1.2GW offshore wind farm located 23km off the Polish coast, marking the conclusion of main works for the foundation package. The fabrication of these transition pieces, each approximately 20 metres high and weighing up to 350 tonnes, was supported by local factories in Żary, Niemodlin, and Łęknica, utilizing steel primarily sourced from Polish mills. The project, a joint venture between ORLEN Group and Northland Power, is currently undergoing wind turbine installation and cable laying, with around 20 vessels active daily. Contractor Van Oord deployed a heavy lift vessel with twin cranes capable of lifting 2,000 tonnes to enhance installation efficiency.
Counterparts (4)
Register free to access full counterpart details, deal analysis, and timeline.
Register free →Deal Analysis
- 1.2 GW offshore wind farm capacity
- 76 transition pieces installed
- Project located 23km off the Polish coast
- Joint venture between ORLEN Group and Northland Power
- Van Oord deployed a heavy lift vessel with twin cranes
Source Intelligence
Each transition piece measures approximately 20 metres in height and weighs up to 350 tonnes. The fabrication of these transition pieces was supported by local factories in Żary, Niemodlin, and Łęknica, utilizing steel primarily sourced from Polish mills. Around 20 vessels are active daily at the site. Van Oord's heavy lift vessel is equipped with twin cranes with a combined lift capacity of 2,000 tonnes.
"Baltic Power has successfully installed all 76 transition pieces at its 1.2GW offshore wind farm located 23km off the Polish coast, marking the conclusion of main works for the foundation package."
"The project, a joint venture between ORLEN Group and Northland Power, is currently undergoing wind turbine installation and cable laying, with around 20 vessels active daily."
"The project, a joint venture between ORLEN Group and Northland Power, is currently undergoing wind turbine installation and cable laying, with around 20 vessels active daily."
"Contractor Van Oord deployed a heavy lift vessel with twin cranes capable of lifting 2,000 tonnes to enhance installation efficiency."