Bilfinger selected by Ocean Winds to provide technical advisory services for BC-Wind offshore wind project in Poland
Type: Supply Agreement · Technology: Offshore Wind · Country: Poland · Capacity: 390 MW · Announced: 2026-08-14
International industrial services provider Bilfinger secured a technical advisory contract from Ocean Winds to oversee key offshore construction activities for the BC-Wind offshore wind project in the Polish Baltic Sea. The 390 MW project, located 23 kilometers from the Polish coastline, involves the installation of 26 wind turbines and is expected to supply electricity to nearly half a million Polish households upon completion in 2028. Bilfinger will supervise turbine installation, offshore structures, and export cable installation while ensuring compliance with technical requirements, permits, and regulations throughout the project lifecycle. The contract follows Bilfinger's prior support for the onshore substation and export cable route, demonstrating the client's confidence in the company's offshore project execution capabilities. Ocean Winds, a 50-50 joint venture between EDP Renewables and ENGIE, reached financial close for the project in late 2025, marking its first offshore wind venture in Poland.
Analysis
Bilfinger has been selected by Ocean Winds to provide technical advisory services for the 390 MW BC-Wind offshore wind project in Poland, located 23 kilometers from the Polish coastline. Ocean Winds, a 50-50 joint venture between EDP Renewables and ENGIE, has a global presence with projects across Europe, Asia, and Australia. Bilfinger will oversee key offshore construction activities, including turbine installation, offshore structures, and export cable installation, for the project which is expected to supply electricity to nearly half a million Polish households upon completion in 2028. The contract was announced on 2026-08-14, following Ocean Winds' financial close for the project in late 2025. The project involves the installation of 26 wind turbines.
Key points
- 390 MW project capacity
- 26 wind turbines to be installed
- Project located 23 kilometers from the Polish coastline
- Expected completion in 2028
- Contract announced on 2026-08-14
Counterparties
- Bilfinger (Supplier)
- Ocean Winds (Developer)
📈 The Sherpa Signal — one notable infrastructure deal a day.