Xcel Energy to power new Google data center in Pine Island, Minnesota
Type: Ppa · Technology: Data Center · Country: United States · Capacity: 1900 MW · Announced: 2026-03-11
Xcel Energy secured an Electric Service Agreement to provide up to 300 MW of reliable power for Google's new hyperscale data center in Pine Island, Minnesota. This long-term deal supports.
Analysis
Xcel Energy has secured an Electric Service Agreement to supply 300 MW of power to Google's new 1900 MW hyperscale data center in Pine Island, Minnesota. This long-term PPA-type arrangement provides Xcel Energy with a substantial, stable load in its Minnesota service territory, supporting its grid modernization efforts. For Google, the deal ensures a reliable power source for a significant portion of its developing 1900 MW facility in Pine Island, Minnesota, a critical component for its operational readiness. The announced 2026-03-11 agreement, while not disclosing value, demonstrates a direct utility-to-corporate power procurement strategy for a large-scale industrial consumer. This agreement aligns with Xcel Energy's increasing focus on renewable energy development and grid modernization as a major U.S. utility. Securing a 300 MW load from Google's Pine Island data center provides a clear demand signal for Xcel Energy's future generation and transmission investments in Minnesota. Google, an active offtaker with 7 verified deals, including nearly 1.2 GW of carbon-free energy via PPAs with Clearway, continues to expand its dedicated energy procurement strategy across the United States. The 300 MW deal in Pine Island, Minnesota, further diversifies Google's energy portfolio, which includes solar investments in Massachusetts.
Key points
- Xcel Energy to supply 300 MW to Google's new data center.
- Google's new hyperscale data center has a 1900 MW capacity in Pine Island, Minnesota.
- The deal is an Electric Service Agreement, a PPA type.
- Google has secured 7 verified deals, including nearly 1.2 GW of carbon-free energy via PPAs with Clearway.
- The agreement was announced on 2026-03-11.
Counterparties
- Google (Offtaker)
- Xcel Energy (Developer)