Avangrid completed panel installation at its 166 MW DC Tower Solar facility in Morrow County, Oregon. Electricity will be delivered to Portland General Electric's grid, supporting a Q.
Get daily solar deal alerts — free, no spam.
Counterparts (4)
supplier
SEG Solar
company · 1 deals
SEG Solar is a high-tech company founded in 2021, specializing in the development, manufacturing, and sales of PV modules. Headquartered in Santa Ana, California, USA, it supplies modules for utility-scale solar projects globally, with a significant presence in the US, Europe, Asia, Latin America, and the Middle East.
Offtaker
QTS
company · 2 deals
QTS Realty Trust, now owned by Blackstone, is a leading provider of data center solutions across a diverse footprint in North America and Europe. They offer a comprehensive portfolio of services, including colocation, hybrid cloud, and hyperscale solutions.
Portland General Electric (PGE)
company · 1 deals
Portland General Electric is an integrated electric utility company based in Portland, Oregon, serving over 900,000 customers across 51 cities. The company owns and operates a diverse portfolio of generation assets, including hydropower, thermal, wind, and solar, and manages transmission and distribution infrastructure.
Register free to access full counterpart details, deal analysis, and timeline.
Register free →
Deal Analysis
The completion of panel installation at Avangrid's 166 MW DC Tower Solar facility in Morrow County, Oregon, marks a critical construction milestone, advancing a substantial renewable asset for the diversified energy company. This development positions Avangrid to deliver significant clean energy capacity to Portland General Electric's grid, aligning with the utility's stated focus on transitioning to cleaner energy sources for its Oregon customers. The commercial logic extends beyond the direct utility off-take, as the electricity generated is specifically earmarked to support QTS, a leading data center provider now owned by Blackstone. This indirect procurement structure allows QTS to meet its energy demands with renewable power, likely fulfilling corporate sustainability objectives without directly managing a power purchase agreement. For Avangrid, progressing this 166 MW project towards operation enhances its renewable generation portfolio and secures future revenue streams from a key regional utility.
Avangrid, as the developer, continues to execute on its core strategy of developing, constructing, and operating renewable energy facilities, with the Tower Solar project in Boardman, Oregon, adding significant scale to its portfolio. The PV modules for this 166 MW facility are supplied by SEG Solar, a high-tech company founded in 2021 and headquartered in Santa Ana, California, demonstrating its rapid emergence as a supplier for utility-scale projects. Portland General Electric, a vertically integrated electric utility serving Oregon, benefits by integrating 166 MW of new solar capacity, directly supporting its mandate to provide reliable, affordable, and cleaner energy to its customer base. Crucially, the ultimate beneficiary, QTS, a data center solutions provider with a diverse North American and European footprint, leverages this project to power its operations, illustrating the increasing demand from large corporate energy users for dedicated renewable supply, often facilitated through utility partnerships.
- Avangrid completed panel installation for its 166 MW DC Tower Solar facility.
- Electricity from the Morrow County, Oregon project will support QTS, a data center provider owned by Blackstone, via Portland General Electric's grid.
- SEG Solar, a company founded in 2021, supplied PV modules for the 166 MW facility.
- The Tower Solar project is located in Boardman, Oregon, United States.
Source Intelligence
KEY DETAILS
The facility also has a generation capacity of 120 MW AC. It utilized more than 250,000 SEG Solar modules assembled domestically at a Houston manufacturing facility. The installation occupies about 900 acres of industrial land owned by the Port of Morrow. Construction activity created approximately 200 jobs, largely filled by regional union labor. Electricity generated will support operations of a QTS data center campus in the region.
Quotes: "The PV facility located in Morrow County west of Boardman has a generation capacity of 166 MW DC and 120 MW AC.", "According to the company statement, the installation has included more than 250000 SEG Solar modules assembled domestically at a Houston manufacturing facility.", "The Tower Solar installation occupies about 900 acres of industrial land owned by the Port of Morrow.", "Construction activity for the Oregon PV facility created approximately 200 jobs which were largely filled by regional union labor.", "Electricity generated from the installation will be delivered to Portland General Electric’s grid and will support operations of a QTS data center campus in the region."
“
Capacity
The PV facility located in Morrow County west of Boardman has a generation capacity of 166 MW DC and 120 MW AC.
“
Location
Avangrid completes Tower Solar installation in Oregon... The PV facility located in Morrow County west of Boardman... The Tower Solar installation occupies about 900 acres of industrial land owned by the Port of Morrow.
“
PPA Details
Electricity generated from the installation will be delivered to Portland General Electric’s grid and will support operations of a QTS data center campus in the region.
“
COD
Commercial operation of the Oregon PV installation is expected later this year
PARTIES MENTIONED IN SOURCE
A
Avangrid
developer
"Avangrid, a US-based energy company operating electricity networks and power generation assets, has completed panel installation at the Tower Solar facility in Oregon."
S
SEG Solar
supplier
"According to the company statement, the installation has included more than 250000 SEG Solar modules assembled domestically at a Houston manufacturing facility."
P
Portland General Electric
buyer
"Electricity generated from the installation will be delivered to Portland General Electric’s grid and will support operations of a QTS data center campus in the region."