Digital Realty to develop sixth data center in Marseille, France
Digital Realty has received approval to convert a 26,000 sqm warehouse in Bouc-Bel-Air, north of Marseille, into its sixth data center in the region. The company plans to invest €700 million ($811 million) to develop the 50MW facility, which will include seven data halls and a new high-voltage power supply from RTE's Realtor substation. Construction is expected to begin in 2026, with servers coming online in 2028.
Counterparts (2)
Subscribe to access full counterpart details, deal analysis, and timeline.
Subscribe from €20/mo →Deal Analysis
- €700 million ($811 million) investment.
- 50MW capacity, Digital Realty's sixth Marseille facility.
- Converts 26,000 sqm warehouse in Bouc-Bel-Air.
- New high-voltage power from RTE's Realtor substation.
Source Intelligence
The project involves converting a 26,000 sqm (279,861 sq ft) warehouse. The facility will accommodate seven data halls. A new high-voltage power supply will run from power company RTE’s Realtor substation in Cabriès, supplying 225,000 volts to a substation at the data center. Server racks at the data center are set to require 120kW each. Construction is hoped to begin in 2026. Quotes: - "The colo giant has received the green light to convert a 26,000 sqm (279,861 sq ft) warehouse in Bouc-Bel-Air, a town just north of Marseille, into a data center." - "converting the building so that it can accommodate seven data halls." - "Digital Realty plans to install a new high-voltage power supply. This will run from power company RTE’s Realtor substation in Cabriès, and supply 225,000 volts to a substation at the data center." - "With server racks at the data center set to require 120kW each, presumably to host AI workloads, Digital Realty plans to install a new high-voltage power supply." - "Digital Realty hopes to begin construction at the data center this year" (referring to 2026, based on article date March 11, 2026).
"Digital Realty has been granted permission to build its sixth data center in Marseille, France."
"This will run from power company RTE’s Realtor substation in Cabriès"