Deals Counterparts

Edify Energy selects DT Infrastructure as preferred EPC contractor for 1.08 GW solar and 900 MW / 3,600 MWh BESS projects in Queensland, Australia

Supply Agreement Hybrid announced Townsville, Australia Mar 4, 2026
1.08 GW
Capacity
development
Stage
The Smoky Creek and The Guthrie’s Gap projects, The Ganymirra and Majors Creek projects
Project

Edify Energy has selected DT Infrastructure as the preferred EPC contractor for two large hybrid solar and battery projects in Queensland, Australia, totaling 1.08 GW of solar and 900 MW / 3,600 MWh of battery storage.

Deal Analysis

Edify Energy has announced the selection of DT Infrastructure as the preferred EPC contractor for two substantial hybrid solar and battery energy storage system (BESS) projects in Queensland, Australia. This supply agreement involves a combined capacity of 1.08 GW of solar generation and 900 MW / 3,600 MWh of battery storage. This announcement, made on 2026-03-04, marks a critical milestone in the development phase, signaling a firm commitment to advancing these large-scale renewable energy assets. The deal is notable for its immense scale, positioning these projects among the largest of their kind globally and significantly contributing to Australia's renewable energy targets. The integration of substantial solar generation with a large-duration BESS capacity (3,600 MWh) is strategically important for providing dispatchable, firm power, enhancing grid stability, and managing intermittency inherent in renewable sources. The selection of a preferred EPC contractor like DT Infrastructure underscores the project's progression towards financial close and subsequent construction, highlighting the developer's confidence in moving forward with these complex, multi-gigawatt assets. This development occurs within the broader context of Australia's accelerating energy transition, particularly in Queensland, which is actively pursuing ambitious renewable energy targets. Hybrid projects combining solar and BESS are increasingly vital for decarbonizing the grid, ensuring energy security, and facilitating the retirement of fossil fuel power plants. Such large-scale infrastructure investments are instrumental in shaping the future energy landscape of the region.
  • Massive scale: 1.08 GW solar and 900 MW / 3,600 MWh BESS.
  • Hybrid technology: Combines large-scale solar generation with significant battery storage.
  • Strategic location: Queensland, Australia, a key region for renewable energy expansion.
  • Key development milestone: Selection of preferred EPC contractor for project execution.

Source Intelligence

KEY DETAILS

The projects include 900 MW / 3,600 MWh of BESS capacity. Hybrid projects will deploy grid-forming inverters designed to improve grid stability and resilience. Pre-construction and design work are underway with construction planned to begin across Q1 and Q2 2026.

Capacity
Overall, the two developments will add about 1.08 GWp of solar capacity and 900 MW / 3,600 MWh of BESS capacity.
Location
Queensland, Australia. The Smoky Creek and The Guthrie’s Gap projects in Banana Shire will include 720 MW of solar and 600 MW / 2,400 MWh battery energy storage system. The Ganymirra and Majors Creek projects in the Townsville region will add 360 MW of solar with 300 MW / 1,200 MWh of battery storage.
PARTIES MENTIONED IN SOURCE
E
Edify Energy developer

"Sydney headquartered Edify Energy has selected DT Infrastructure as the preferred EPC contractor"

D
DT Infrastructure EPC contractor

"DT Infrastructure as the preferred EPC contractor"

medium quality Enriched Mar 4, 2026

Timeline

Announced
Mar 4, 2026
Signed
Closed