After originally buying 375 acres, Google later acquired another 165-acre tract for further development at its Midlothian campus.

Deal Analysis

Google has announced the acquisition of an additional 165-acre tract for further data center development at its Midlothian campus in the USA. This acquisition expands upon an initial 375-acre purchase, signaling a significant long-term investment in its digital infrastructure footprint. While the deal value remains undisclosed, the strategic nature of this land banking for future capacity is evident, positioning Google for sustained growth in its data center operations. This transaction highlights Google's proactive approach to meeting future demand in the data center sector. As a major player, Google is consistently active as both an offtaker and buyer, with 7 verified deals, including securing nearly 1.2 GW of carbon-free energy via PPAs. The expansion of an existing campus through additional land acquisition underscores a deliberate strategy to ensure scalable growth and operational continuity for its critical services.
  • Buyer: Google, a major global technology company and infrastructure developer.
  • Asset: Additional 165-acre tract for data center development, expanding an existing campus.
  • Sector: Data center, indicating robust demand for digital infrastructure.
  • Strategic Move: Land banking for future capacity and long-term growth.

Source Intelligence

KEY DETAILS

The project will be a one-story data center spanning 288,000 sq ft (26,756 sqm). The investment will include the core, shell, and interior finish out, as well as site improvements. The construction project began in late January 2026. Google originally bought 375 acres and later acquired another 165-acre tract for further development at its Midlothian campus. Google launched a Texas cloud region in Dallas in June 2022. Google is also developing a second Texas campus in the Red Oak area of Dallas. In November 2025, Google revealed it would spend $40bn to expand its cloud and AI infrastructure in Texas through 2027, including expansion in Ellis County and new campuses in Armstrong and Haskell Counties.

Deal Size
An estimated $880 million will be invested in the development
Location
Google has filed to build another data center at its campus in Midlothian, Texas. ... The location of the project is listed as 3441 Railport Parkway in Ellis County, the same address as Google's Midlothian data center campus.
Announcement
March 03, 2026 By Georgia Butler Have your say Google has filed to build another data center at its campus in Midlothian, Texas.
COD
is expected to be completed by February 24, 2027.
Expected Close
is expected to be completed by February 24, 2027.
PARTIES MENTIONED IN SOURCE
G
Google developer

"Google has filed to build another data center at its campus in Midlothian, Texas."

S
Sharka LLC developer

"Google - through the shell company Sharka LLC, which was behind the other data centers for Google at the site - has shared its plans for a fifth building on the data center campus."