Pacifico Energy is developing the GW Ranch project, a private-grid power generation campus in West Texas, designed for hyperscale data centers and AI innovation, with up to 7.65 GW of power generation utilizing a mix of small and large-scale gas turbines, integrated with battery storage and solar.
Deal Analysis
Pacifico Energy's GW Ranch project represents a significant development in private-grid power generation tailored for the burgeoning hyperscale data center and AI innovation sectors. Located in West Texas, the project aims to deliver up to 7.65 GW of power through a diversified energy mix, including gas turbines, battery storage, and solar. This integrated approach seeks to provide a reliable and potentially more sustainable power source for energy-intensive operations. The involvement of the Texas Commission on Environmental Quality as a regulator underscores the project's need to meet environmental standards.
Given the increasing demand for power from data centers and AI applications, the GW Ranch project could establish a new model for self-sufficient energy infrastructure. The project's scale and the integration of multiple power generation technologies are particularly noteworthy. While the project value remains undisclosed, the sheer capacity suggests a substantial investment. Pacifico's experience in renewable energy development positions them well to execute the solar and battery storage components of the project.
- 7.65 GW power generation capacity is substantial, indicating a large-scale operation.
- The project targets hyperscale data centers and AI innovation, reflecting the growing demand for power in these sectors.
- The integrated energy mix (gas, solar, battery storage) aims for reliability and potential sustainability.
- Pacifico Energy, a renewable energy company, is leading the development.
Market Context: The data center market, particularly for hyperscale facilities, is experiencing rapid growth, driving demand for reliable and cost-effective power solutions. West Texas is becoming an increasingly attractive location for energy-intensive industries due to its favorable energy resources and regulatory environment.
Source Intelligence
KEY DETAILS
Project Highlights Up to 7.65 GW of dispatchable generators, integrated with 1.8GW battery storage and up to 750MWac Solar Enables a rapid development timeline: Q1 2027 first power. 1GW online in 2028 and 5+GW capacity in 2031 Redundant system design provides over 99.99% availability 8,000+ acres site with space for future expansion
“
Capacity
air permit of up to 7.65 GW of power generation utilizing a mix of small and large-scale gas turbines
“
Location
GW Ranch project is a private-grid power generation campus located in West Texas
PARTIES MENTIONED IN SOURCE
P
Pacifico Energy
developer
"Pacifico Energy’s GW Ranch project is a private-grid power generation campus located in West Texas"
high quality
Enriched Feb 19, 2026
Market Context
This deal is part of the Data Center sector in USA.