Hellenic Cables to supply cables for BC-Wind offshore project in Poland

Supply Agreement Offshore Wind announced Poland Mar 7, 2026
390 MW
Capacity
construction
Stage
BC-Wind offshore project
Project

Hellenic Cables will supply approximately 43.4 miles of 66 kV submarine inter-array cables for the 390 MW BC-Wind offshore project in Poland.

Get daily offshore wind deal alerts — free, no spam.

Sign up free to access full counterpart details, deal analysis, and timeline.

Sign up free →

Deal Analysis

Hellenic Cables will supply 43.4 miles of 66 kV submarine inter-array cables for the 390 MW BC-Wind offshore project in Poland, announced 2026-03-07. DEME, a global marine engineering company, is the buyer for the 390 MW project, developed by Ocean Winds, a 50-50 joint venture. This supply agreement advances the 390 MW offshore wind capacity in Poland.
  • Hellenic Cables to supply 43.4 miles of 66 kV submarine cables.
  • Cables for 390 MW BC-Wind offshore project in Poland.
  • DEME is the buyer; Ocean Winds (50-50 JV) is the developer.
  • Supply agreement announced 2026-03-07.

Source Intelligence

KEY DETAILS

Hellenic Cables will be tasked with monitoring the design, engineering, manufacturing, testing, and delivery of approximately 43.4 miles of 66 kV submarine inter-array cables, including spares and accessories. The production process will occur at the company’s modern submarine cable plant in Corinth, Greece. The BC-Wind project is situated about 14.29 miles off Poland’s Baltic Sea coast and intends to deliver clean electricity to approximately half a million homes each year. Hellenic Cables was founded in 1950 and is part of Cenergy Holdings, based in Greece, specializing in power, telecom, and submarine cables for renewable projects, with plants in Greece (Thiva, Eleonas, Corinth) and Romania (Bucharest).

Capacity
The Ocean Winds-operated farm is a 390 MW BC-Wind offshore wind project.
Location
Hellenic Cables to supply cables for the BC-Wind offshore project in Poland.
Announcement
Hellenic Cables to supply cables for the BC-Wind offshore project by Prince March 7, 2026
Expected Close
delivery and completion planned for late 2027.
PARTIES MENTIONED IN SOURCE
H
Hellenic Cables supplier

"Hellenic Cables to supply cables for the BC-Wind offshore project"

D
DEME awarding party

"Belgian marine contractor DEME is the one that has received credit for awarding Hellenic Cables with the monumental contract to supply cables."

O
Ocean Winds developer

"The Ocean Winds-operated farm is a 390 MW BC-Wind offshore wind project."

E
EDP Renewables joint venture partner

"Ocean Winds is the developer of BC-Wind, and it is a 50/50 joint venture between major energy firms EDP Renewables and ENGIE."

E
ENGIE joint venture partner

"Ocean Winds is the developer of BC-Wind, and it is a 50/50 joint venture between major energy firms EDP Renewables and ENGIE."

high quality Enriched Mar 7, 2026

Timeline

Announced
Mar 7, 2026
Signed
Closed

Get the full picture — timeline, source intelligence, and counterpart analysis.

Sign up free →
Track Offshore Wind deals