Kona Energy Secures £40M Capacity Market Contract for 456MWh Smeaton Battery Storage Project in Scotland
Kona Energy, a UK independent battery storage developer, has secured a circa £40 million Capacity Market contract for its landmark 228MW/456MWh Smeaton battery energy storage system (BESS) in East Lothian, Scotland. This milestone follows successful planning consent and positions Smeaton as a critical asset for grid stability, particularly with the upcoming closure of Torness nuclear power station. The contract, awarded through the T-4 auction, provides a de-risked, index-linked revenue stream and enhances grid connection certainty, crucial for investor confidence. Detailed design work is underway with Scottish Power Transmission, and Kona Energy is actively seeking strategic partners for the project's next phase of delivery.
Counterparts (3)
Deal Analysis
- Secured £40 million Capacity Market contract for a 228MW/456MWh BESS.
- Project is critical for Scottish grid stability, especially with Torness nuclear power station closure.
- Contract provides a de-risked, index-linked revenue stream, enhancing investor confidence.
- Large-scale project in development, moving towards delivery with strategic partners.
Source Intelligence
The project secured its Capacity Market agreement in the T-4 auction - a government-backed mechanism ensuring electricity supply during peak demand. The contract provides an attractive index lined revenue contract and a de-risked grid connection. The project benefits from two ‘Protections’ under the ongoing Grid Connection Reform and Clean Power 2030 plan. Strategic investment discussions are ongoing, and Kona Energy is actively engaging with select strategic partners to bring expertise and capital for the project's delivery. Quote: "The project secured its Capacity Market agreement in the T-4 auction - a government-backed mechanism ensuring electricity supply during peak demand." Quote: "this contract not only provides an attractive index lined revenue contract but as importantly a de-risked grid connection which is crucial to investor confidence’" Quote: "The project benefits from two ‘Protections’ under the ongoing Grid Connection Reform and Clean Power 2030 plan" Quote: "with strategic investment discussions ongoing." Quote: "we are actively engaging with select strategic partners who can bring the right expertise and capital to maximise the project’s potential"
"Kona Energy, one of the UK’s leading independent battery storage developers"
"commitment from NESO to bring projects online ahead of their Capacity Market delivery year"
"Detailed design work is already underway in partnership with Scottish Power Transmission"