Moray West lenders and sponsors discuss loan waiver after PPA milestone missed
By Global Infrastructure Sherpa · Feb 25, 2026
Ocean Winds and Ignitis are in discussions with their lenders after a contractual milestone for an unnamed off-take agreement was missed last September, representing an event of default under the project lending agreements for the 882MW Moray West wind farm.
Deal Analysis
Ocean Winds and Ignitis, the sponsors of the 882MW Moray West wind farm project in Scotland, are currently in discussions with their lenders regarding a potential loan waiver. This situation arose after the project missed a contractual milestone related to an unnamed off-take agreement in September, triggering an event of default under the project's lending agreements. The ongoing negotiations suggest a need for restructuring or revised terms to ensure the project's continued financing and progression towards completion. The outcome of these discussions will be critical for the future of the Moray West project and could influence investor confidence in similar renewable energy ventures.
The missed milestone and subsequent loan waiver discussions highlight the inherent risks associated with large-scale renewable energy projects, particularly those reliant on power purchase agreements (PPAs). While the specific details of the missed milestone remain undisclosed, it underscores the importance of robust risk management and contingency planning in project finance. The involvement of established players like Ocean Winds and Ignitis, coupled with the project's substantial 882MW capacity, makes this situation noteworthy within the renewable energy finance landscape. The resolution of this event will be closely watched by industry participants.
- 882MW Moray West wind farm project facing potential loan waiver.
- Missed PPA milestone triggered event of default under project lending agreements.
- Ocean Winds and Ignitis are in discussions with lenders.
- Project located in Scotland.
Market Context: The wind energy sector is a key component of the global transition to renewable energy. Scotland is an important region for wind energy development.
Source Intelligence
KEY DETAILS
A contractual milestone for an unnamed off-take agreement was missed last September. "This delay in achieving the contractual milestone represents an event of default under the project lending agreements," according to the project accounts. An outage is affecting half of the power at the 882MW Moray West wind farm. The outage affects one of the project’s two offshore substations and has been active since November.
“
Capacity
882MW Moray West
“
Location
882MW Moray West wind farm off north-east Scotland
“
PPA Details
after a contractual milestone for an unnamed off-take agreement was missed last September.
“
Announcement
25 February 2026 14:25
“
COD
Commercial operations, which had been due last year, are expected to start in 2026, according to the accounts.
PARTIES MENTIONED IN SOURCE
O
Ocean Winds
developer
"Ocean Winds and Ignitis have suffered an outage affecting half of the power at the 882MW Moray West wind farm off north-east Scotland."
I
Ignitis
developer
"Ocean Winds and Ignitis have suffered an outage affecting half of the power at the 882MW Moray West wind farm off north-east Scotland."
L
Lenders
lender
"The Company and Lenders have agreed a short-term waiver to extend the cure period and are currently in discussions for a further extension."
medium quality
Enriched Feb 25, 2026
Market Context
This deal is part of the Wind sector in Scotland.
1 of 137 Wind deals tracked this month · Updated daily