Oncor and LCRA TSC to build 765kV transmission line
By Global Infrastructure Sherpa · Jan 15, 2026
Big Hill Switch to Sand Lake Switch 765kV Transmission Line Project
Project
Oncor and LCRA TSC have filed an application to build a 765kV transmission line from Ward to Schleicher counties to strengthen the Texas transmission grid. The proposed line will be approximately 197 miles long and is expected to be energized by the winter of 2030, pending PUCT approval.
Deal Analysis
Oncor and LCRA Transmission Services Corporation (LCRA TSC) have announced a joint development to construct a 197-mile, 765kV transmission line in Texas, connecting Ward and Schleicher counties. The project, currently pending approval from the Public Utility Commission of Texas (PUCT), aims to bolster the state's transmission grid and is projected to be operational by winter 2030. While the deal value remains undisclosed, the involvement of Oncor, a major electric delivery company serving over 3.8 million customers, and LCRA TSC, alongside regulatory oversight from the PUCT, underscores the project's importance for grid reliability and future energy needs in Texas.
This development signifies a crucial investment in Texas's energy infrastructure, addressing the increasing demand for electricity and the need for a more robust and resilient grid. The construction of a high-voltage transmission line will enhance the capacity to move power across the state, potentially unlocking renewable energy resources and improving overall grid stability. The project's success hinges on timely regulatory approvals and efficient execution by Oncor and LCRA TSC, both experienced players in the Texas energy market.
- Oncor and LCRA TSC are jointly developing a 197-mile, 765kV transmission line.
- The project is pending approval from the Public Utility Commission of Texas (PUCT).
- The line is expected to be energized by winter 2030.
- Oncor is a major electric delivery company serving over 3.8 million customers.
Market Context: Texas has a deregulated electricity market and is experiencing rapid population and economic growth, driving increased demand for electricity and necessitating investments in transmission infrastructure to ensure grid reliability and support the integration of renewable energy sources.
Source Intelligence
KEY DETAILS
The proposed line will be approximately 197 miles, depending on the final route approved by the PUCT. Preliminary route links submitted for PUCT consideration are located in Crane, Crockett, Irion, Pecos, Reagan, Reeves, Schleicher, Tom Green, Upton and Ward counties.
“
Location
Oncor and LCRA Transmission Services Corporation (LCRA TSC) have taken a significant step toward building a 765kV transmission line from Ward to Schleicher counties
“
Announcement
DALLAS, January 15, 2026
“
COD
if approved, Oncor and LCRA TSC anticipate the line will be energized by the winter of 2030.
PARTIES MENTIONED IN SOURCE
O
Oncor
developer
"Oncor and LCRA Transmission Services Corporation (LCRA TSC) have taken a significant step toward building a 765kV transmission line from Ward to Schleicher counties"
L
LCRA TSC
developer
"Oncor and LCRA Transmission Services Corporation (LCRA TSC) have taken a significant step toward building a 765kV transmission line from Ward to Schleicher counties"
high quality
Enriched Feb 19, 2026
Market Context
This deal is part of the Transmission sector in United States.
565
deals in United States
1 of 139 Transmission deals tracked this month · Updated daily