Pure DC and AVK launch 110MW natural gas microgrid at Dublin data center campus
110 MW
Capacity
Pure Data Centres (Pure DC) and power firm AVK announced the launch of a 110MW on-site microgrid at Pure DC's Dublin campus. This project, billed as Europe's first large-scale microgrid, will support early-phase data center operations ahead of full grid connection and is engineered to accommodate future hydrogen blending and includes Combined Heat and Power (CHP) capability and a battery energy storage system (BESS). The microgrid will be comprised of three interconnected energy centers, with EC1 and EC2 operational by the end of 2026.
Get daily data center deal alerts — free, no spam.
Counterparts (2)
Partner
Pure Data Centres (Pure DC)
London-based Pure Data Centres Group is a developer and operator of hyperscale data centres, established in 2015. The company focuses on expanding its portfolio across key markets in Europe and Asia Pacific.
A
AVK
AVK is a Danish industrial manufacturer of valves, hydrants, and accessories for water, gas, wastewater, and fire protection. With over 4,900 employees, the company operates globally, supplying critical components for utility infrastructure networks.
Subscribe to access full counterpart details, deal analysis, and timeline.
Subscribe from €20/mo →Deal Analysis
Pure DC and power firm AVK are deploying a 110MW natural gas microgrid at Pure DC's Dublin data center campus, a move designed to get early operations online ahead of full grid connection. Billed as Europe's first large-scale microgrid, this partnership addresses critical power supply challenges in a rapidly expanding market. The system is engineered for future flexibility, incorporating hydrogen blending capability, combined heat and power, and a battery energy storage system. With two of its three energy centers expected online by the end of 2026, this project offers a template for data center development in power-constrained regions.
- 110MW natural gas microgrid capacity
- Europe's first large-scale microgrid
- Future-proofed with hydrogen blending, CHP, and BESS
- Two energy centers operational by end of 2026
Timeline
Announced
Mar 12, 2026
Signed
Closed
Get the full picture — timeline, source intelligence, and counterpart analysis.
Subscribe from €20/mo →
Global Infrastructure Sherpa