Deals Counterparts

TransAlta, CPP Investments, and Brookfield Asset Management partner for large-scale data centre development in Alberta

Partnership Data Center announced Canada Feb 28, 2026
230 MW
Capacity
development
Stage

TransAlta Corporation, Canada Pension Plan Investment Board, and Brookfield Asset Management have entered into a memorandum of understanding to advance a large-scale data centre development in Alberta. TransAlta will serve as the exclusive site and power provider for the project at its Keephills facility, with an initial long-term power purchase agreement of approximately 230 megawatts and potential to scale up to 1 gigawatt.

Deal Analysis

TransAlta Corporation, Canada Pension Plan Investment Board (CPP Investments), and Brookfield Asset Management have announced a strategic memorandum of understanding to advance a large-scale data centre development in Alberta. This partnership designates TransAlta as the exclusive site and power provider for the project at its Keephills facility. The initial phase includes a long-term power purchase agreement for approximately 230 megawatts, with substantial potential to scale up to 1 gigawatt, underscoring the project's significant ambition and long-term vision. This collaboration brings together a major utility with two prominent global infrastructure investors, signaling a significant commitment to digital infrastructure development in Canada. The involvement of CPP Investments and Brookfield Asset Management highlights the attractiveness of large-scale, power-intensive data centre projects for institutional capital seeking stable, long-term returns. Leveraging TransAlta's existing energy infrastructure provides a foundational advantage, enabling the rapid deployment and scaling of critical digital capacity to meet the escalating demands of the data centre sector.
  • Partnership between a utility (TransAlta) and two global infrastructure investors (CPP Investments, Brookfield Asset Management).
  • Large-scale data centre development with initial 230 MW capacity and potential to scale up to 1 GW.
  • TransAlta serving as exclusive site and power provider, leveraging its Keephills facility.
  • Long-term power purchase agreement (PPA) as a core component of the deal.

Timeline

Announced
Feb 28, 2026
Signed
Closed